Week three was a pretty big transformation. We started Monday with a completely clear lot:
By Friday afternoon, the foundation was framed and ready for the plumber:
The plumber should start today and be done by Friday. Once everything is approved, the foundation will be poured. After that, things will come to a stop on the house and the pool will start. The pool will be in the back right hand corner of the lot and should be very close to the back patio. Since it is so close to the house, they want to dig the hole before the house gets too far along.