Wednesday, November 25, 2015

Walls!!

The framers started yesterday and we already have a couple walls up! Scott is hoping the first floor will be framed by the beginning of next week.


Friday, November 20, 2015

Pool

The pool took almost 3 weeks but should be complete today!

We have had some rain delays but everything is moving right along.







Framing is set to begin Tuesday but we may run into some weather delays again next week. Fingers crossed they can start and finish on time!

Monday, November 2, 2015

Foundation and Lots of Rain

The foundation is done!!! We had a bit of a rain delay last week. Monday & Tuesday were spent fixing the damage but Wednesday morning brought 12 trucks of cement and the whole process was over by 4 PM.










The Workers loved my boots.


The pool was marked and staked but because of more rain, the inspection was delayed until today.  We are hoping to start digging Tuesday but it is also suppose to rain again this weekend.